Now that the summer is back, fieldwork program for Cima del Simano instability will start for this year !
This planning is as follow for 2022 :
- June : Installation of the GB-Insar for a 2 weeks acquisition.
- July : Lidar acquisition, preparation for the installation of extensometers in some choosen fractures, GPS campaign and rock samplings for further geotechnical tests that will improve the numerical modellings.
- August : Installation of the automated extensometers measuring the daily opening and closure of some fractures.
- September : Second GB-Insar compaign for 2 weeks, second GPS campaign
- October : Removal of the GB-Insar