CLE – Installation MILabs system final schedule

Here is the updated schedule for the MIlabs installation.

– Tuesday Oct 15th
Unloading, Unpacking, Inspection of the system, System Placement, Power up.

Wednesday Oct 16th
Mechanical checks, Mechanical Calibrations, CT start up.

Thursday Oct 17th
CT Mechanical Checks, CT safety.

Friday Oct 18th
CT Quality Assurance Scans, Emission Detector Calibration.

-Monday Oct 21st
Optical Installation and Calibration.

Tuesday Oct 22nd
Optical Quality Assurance.

Wednesday Oct 23rd & Thursday Oct 24th
User training and Customer Acceptance.

AGORA – update on the X-RAD SmART (PXI)

Most of the installation and commissioning have been performed last week. We are still missing the 5 mm collimator. We have had a setback in completion of the training. A small piece that controls the mechanical opening/closing of shutter of the detector broke. A technician is coming on Thursday 10th of October for reparation. Finally the commissioning for the missing collimator should be performed next week.