Here is the updated schedule for the MIlabs installation.
– Tuesday Oct 15th
Unloading, Unpacking, Inspection of the system, System Placement, Power up.
–Wednesday Oct 16th
Mechanical checks, Mechanical Calibrations, CT start up.
–Thursday Oct 17th
CT Mechanical Checks, CT safety.
–Friday Oct 18th
CT Quality Assurance Scans, Emission Detector Calibration.
-Monday Oct 21st
Optical Installation and Calibration.
–Tuesday Oct 22nd
Optical Quality Assurance.
–Wednesday Oct 23rd & Thursday Oct 24th
User training and Customer Acceptance.